Pre-completion steps (buyer's solicitor)

Pre-completion searches — must be done immediately before completion:

  • OS1 (whole) / OS2 (part) — official search with priority of the registered title at HM Land Registry. Priority starts when the search application enters the day list and ends at midnight on the 30th working day thereafter. It protects the specified disposition against competing later applications, subject to earlier priority protection. Complete and lodge the protected registration application, including any dealing on which it depends, within that period; HMLR may complete registration afterwards. Where borrowing, search in the lender's name to protect its charge and the purchase on which it depends.
  • K16 — bankruptcy-only search for the lender against the individual buyer/borrower and any individual guarantor, whether the land is registered or unregistered. It reveals bankruptcy petitions, debtor applications and orders; other entries in the same registers may also appear. Investigate any apparent match. The search is on behalf of the lender, not against the lender. Do not confuse with K15.
  • For unregistered land: K15 Land Charges full search against estate owners' full names for their periods of ownership (catches Class C/D/F charges, etc.). When buying from personal representatives, extend the search against the deceased owner through to the current date, not merely the date of death.

Requisitions on title — final enquiries confirming completion arrangements, redemption figures, undertakings for discharge of seller's mortgage.

Engrossment & pre-completion — final transfer approved: TR1 for a whole registered title, TP1 for part. Arrange execution by the seller and by the buyer where the buyer's covenants or declarations require it; insert the completion date on completion, after execution. Mortgage deed executed where borrowing; completion statement agreed (purchase price, deposit credit, apportionments of e.g. service charge/ground rent).

Completion itself

  • SCS (Standard Conditions of Sale) are commonly incorporated into residential contracts; SCPC into commercial contracts. Check incorporation and special conditions. Under unamended SCS 6.1.2, money received after 2.00 pm means completion is deemed to occur next working day only for apportionments and late-completion compensation. Exception: where vacant possession is required and a ready, able and willing buyer delays payment because the seller has not vacated by 2pm, the delay is attributed to the seller (SCS 6.1.3).
  • Late completion — SCS 7.2: the party with the longer default pays compensation at the contract rate on the price, deducting the deposit only where the buyer pays. Use the excess default period, capped at the interval between contractual and actual completion. If completion is delayed and the buyer is the seller’s tenant, the seller may elect net income until completion under SCS 7.2.4, notifying the buyer before the actual completion date; compensation under SCS 7.2.1 cannot also be claimed.
  • Notice to complete — SCS 6.8: after the contractual completion deadline, a ready, able and willing party may give notice. Completion is then due within 10 working days, excluding the day notice is given; time becomes of the essence. Readiness includes ability to complete but for the other's default; a seller may discharge mortgages from sufficient completion funds. On receiving a notice to complete, the buyer must immediately pay a 10% deposit if none was paid, or top up a smaller deposit to 10%.
  • Failure after notice: seller may rescind for buyer default and retain deposit plus accrued interest; buyer may rescind for seller default and recover deposit plus accrued interest. Other remedies remain available; compensation already paid reduces damages for the same delay.
  • Completion commonly uses the agreed Law Society Code for Completion by Post — buyer's solicitor sends funds; seller's solicitor completes as the buyer's solicitor's limited agent, dates the transfer, holds completion documents to order and arranges release of keys. The seller's solicitor undertakes to redeem or obtain discharge of the specified charges. For paper discharge, supply DS1; for electronic discharge (ED) or e-DS1, the lender sends discharge to HMLR and the seller's solicitor passes on confirmation when received. END is obsolete.

Post-completion (key deadlines — get these right)

  • SDLT (England): for a notifiable transaction, file the return and pay any tax due within 14 days after the effective date — normally completion, but earlier substantial performance can trigger it. Substantial performance includes the buyer or a connected person taking possession of substantially the whole property, or payment of substantial consideration; payment of rent can also trigger it. The standard residential nil-rate band is £125,000; reliefs and higher rates may change liability. For a registrable notifiable purchase, provide SDLT5; a non-notifiable transaction requires no SDLT return or SDLT5.
  • LTT (Wales): submit any required return to the WRA and pay tax due within 30 days beginning the day after the effective date. A notifiable transaction requires the WRA certificate for registration.
  • Registration at HMLR: lodge the protected application within the OS1/OS2 priority period (30 working days); registration itself may finish later. First registration of unregistered land must be applied for within 2 months of completion.

Common traps

  • Confusing OS1 priority (30 working days) with the SDLT 14-day deadline — distinct clocks.
  • Apply the 2pm rule with its seller-default exception. A valid notice to complete gives 10 working days, excluding the day notice is given, and makes time of the essence; the giver must be ready, able and willing to complete.
  • The lender's bankruptcy search (K16) covers the individual buyer/borrower and any individual guarantor. Seller insolvency must also be considered: the K15 full Land Charges search in unregistered conveyancing includes bankruptcy entries against the estate owners searched.
  • Failing to obtain the seller's solicitor's undertaking to redeem or obtain discharge of the specified existing mortgage before releasing completion funds.

Executing the transfer as a deed

A deed must make its intended character clear on its face, be validly executed and be delivered as a deed. For an individual signing personally, a witness must be physically present and attest the signature. Watching by video is insufficient. The alternative statutory method is signature at the individual's direction and in their presence and the presence of two witnesses, who each attest. Delivery means an intention to be bound as a deed, not simply handing over paper. Arrange execution and delivery so that the transfer takes effect on completion.

For an ordinary company, execution can be under its common seal or by two authorised signatories, meaning two directors or a director and company secretary, or by a director signing before an attesting witness. A company deed also requires delivery; delivery is presumed on execution unless a contrary intention is proved. Check authority and use an appropriate execution block. The transferor executes the transfer; a transferee entering a covenant or declaration in it must also execute as appropriate. A buyer's indemnity covenant in TR1 therefore requires the buyer's execution.

Completion figures and apportionments

Start with the price, deduct the deposit already credited and apply the agreed adjustments. Identify separately the lender's advance, the client's funds, fees, tax funding and money needed to discharge existing charges. Avoid crediting a deposit twice.

For each periodic payment, identify the contractual apportionment date, the party responsible for that day, the calculation basis and whether the payment has already been made. Under unamended SCS 6.3, vacant possession normally means apportionment at actual completion; otherwise the contractual completion date applies, subject to the income-election provision. The seller is treated as owner until the end of the apportionment day. SCS use an equal daily rate throughout the year. Apply an agreed special condition instead where it changes that basis.

For example, a special condition may allocate a GBP300 payment for 1 to 10 September by actual days, with the buyer responsible from completion on 5 September. The seller's prepayment then produces a GBP180 credit to the seller: GBP30 multiplied by six days. That allocation of completion day is expressly agreed, not the unamended SCS default. For an unpaid liability, identify who will discharge it and credit that party with the other's contractual share. Use provisional figures where necessary and follow the contractual reconciliation procedure.

Obtain a current redemption statement for every charge to be discharged. Check its validity, the redemption date, daily interest, fees, early repayment charges and any receipts already allowed. Follow the lender's calculation instructions rather than assuming the balance is static. A figure of GBP180,000 for 8 September, plus GBP60 for each further day through redemption on 11 September, becomes GBP180,180. Obtain an updated statement where the existing statement no longer supports the proposed payment. Resolve any shortfall before giving an undertaking that depends on discharge.

Completion methods and surviving obligations

Personal attendance is an available agreed method: the conveyancers coordinate payment and release of the executed transfer and other completion documents directly. It does not remove the need for an effective deed or satisfactory mortgage discharge arrangements. Completion by post instead uses the agreed agency and undertaking arrangements described above.

On completion the contract merges in the transfer so far as the transfer performs it, which discharges the obligation to convey. Merger does not extinguish obligations that the transfer does not perform, and SCS 7.3 provides that completion does not cancel liability to perform any outstanding obligation under the contract. Expressly surviving or collateral obligations also require attention; a promise to finish boundary works after completion is not discharged simply because the transfer omits it. Distinguish contractual completion from the vesting of the registered legal estate: a registrable transfer must be completed by registration under LRA 2002 s.27.

Common-law damages for delayed completion

A claimant must establish breach, causation and recoverable loss. Damages aim to put the claimant in the financial position performance would have produced. Loss must not be too remote: consider ordinary consequences and special circumstances communicated when the contract was made. The claimant must take reasonable steps to mitigate and prove the amount claimed. Reasonable temporary accommodation costs can qualify where the seller's breach causes them and the accommodation need was within the parties' reasonable contemplation when the contract was made.

Check any applicable contractual limitation and avoid double recovery. SCS 7.2.3 reduces damages for delayed completion by contractual compensation already paid for that delay. Thus GBP1,000 of established recoverable loss less GBP200 compensation leaves GBP800 additional damages. Contractual compensation is not itself proof of an additional common-law loss.

Try a real SQE1 question

This question is taken from the bank. Answer it to see the worked reasoning and the tutor. You do not need to sign up to try it.

A woman is the treasurer of a small amateur football club. Members pay £20 each month in cash. Under the club rules she accepted on becoming treasurer, she must bank the subscriptions into the club's dedicated account within seven days. One month she receives £200 in subscriptions and spends the cash on her own gas bill that same day. She intends to replace the money from her wages before anyone notices, and pays an equivalent £200 into the club account two weeks later. Which statement best explains how section 5(3) of the Theft Act 1968 applies to the subscriptions when she pays the gas bill?

Practise at the real standard

Strong on this topic? SQE1 tests 13 subjects, and 58% did not pass in July 2026. See where you stand.

Complete includes

  • ✓An AI tutor on every question. The tutor already knows the correct answer
  • ✓5 full timed mocks (an FLK1 and an FLK2 paper in each), plus unlimited drilling with no daily cap
  • ✓Notes and practice questions for all 13 SQE1 subjects: the whole 2,953-question bank, with worked answers and references
  • ✓Your weak-spot map: the topics where you are losing the most marks
See what it costs →Start the free 25-question diagnostic

One payment, nothing recurring. The 25-question diagnostic is free with no card.

More Property Practice topics

See all topics in the FLK2 guide or the full SQE1 syllabus.

Independent SQE1 revision notes for study, not legal advice; check primary sources before relying on any point. Exam rules are set by the SRA; see the official SQE site.

Pre-completion & completion: SQE1 revision notes (FLK2) | Lawdojo